Law 82-21Decree 2-25-100 in force — existing installation? We prepare your regularization file →

Law 82-21 · decree 2-25-100

Three regimes, only one is yours

Law 82-21 on the self-production of electrical energy and its implementing decree 2-25-100 are in force. From now on, whether it is brand new or already installed, every self-production installation falls under one of the three regimes below — and it is its power and its connection that decide which one.

Where does the law stand? · verified on 5 October 2026

In force

Implementing decree 2-25-100 (in force) and ANRE decision 04/26. ANRE surplus tariff (decision 04/26):0.18 DH/kWh off-peak, 0.21 DH/kWh at peak, excluding taxes, for installations connected at medium, high or very high voltage (MV/HV/EHV), whatever their regime.

Not yet published

In low voltage (LV), whatever the regime — including a shop of 11 kW or more under a connection agreement — resale of the surplus is not open as of today. Do not take the MV/HV tariff above as the one for your home or your shop.

Every tariff figure published on this site carries its validity window and its source; we update this page as soon as the residential LV tariff is published.

Instant assessment

Which regime applies to your installation?

Three questions, an immediate answer.

Applicable regime

    Have my file checked

    Reference

    The three regimes in detail

    Declaration regime

    Installations under 11 kW connected at low voltage, or installations not connected to the grid (off-grid sites). A prior declaration is enough.

    • File a declaration before commissioning
    • Meet the technical connection requirements (if grid-connected)
    • Keep the declaration filing receipt

    Connection-agreement regime

    Grid-connected installations, from the declaration threshold up to 5 MW, at low or medium voltage. A connection agreement with the grid operator is required before commissioning.

    • Obtain the grid operator’s connection agreement before commissioning
    • Install a compliant metering device
    • Comply with the technical terms of the agreement (injected power, protections)

    Authorization regime

    Installations of 5 MW and above, connected at medium, high or very high voltage. A prior authorization is required.

    • Obtain the authorization before any works begin
    • Compile a complete technical file (connection study, diagrams, compliance)
    • Comply with ANRE monitoring and oversight

    Existing installations

    Already have an undeclared installation?

    For installations already in place, Article 33 of the law provides for regularization "within eighteen (18) months from the date of entry into force of this law" (Law 82-21, art. 33 — text of dahir 1-23-21 linked in this page's official sources). The step-by-step procedure is detailed on the dedicated page.

    Regularize my installation

    Official texts and where to file

    The file (declaration or grid-connection agreement request) is filed with the distribution network operator concerned by your connection.

    The texts, at the source:

    Free study

    Unsure about your regime? We check it for free.

    Have my file checked

    Free · No obligation · WhatsApp reply within 1 h, 7 days a week